TECHNICAL CONDITIONS

Technical conditions  - are the technical requirements of the electrical transmitting organization, the fulfilment of which is necessary for object connection to the electrical networks. optimum TC connection of the Customer’s facility to external electrical networks. The specialists of the company analyze the existing electrical networks in the area of the site of the Customer in order to determine the optimal option of object connection to the electrical networks.

 

 

 

 

In order to obtain the Treaty and TС, it is necessary to submit to the Electricity Transmitting Organization an application to join the electrical installation, which contains the following data: details of the customer, the capacity of the facility, the timetable for the power input, the mode of operation, etc.

The application shall be accompanied by such documents as:

  • situational plan and mapping of the topographical and geodetic plan at scale of 1:2000, indicating the location of the site;
  • copy of the document which confirms the ownership or use of the facility or, in the absence of the facility, the ownership or use of the land;
  • copy of the power of attorney to conclude contracts for the individual authorized to sign the contracts.

 

 

 

 

Depending on type of object connection to electrical networks, several types of TС differ:

 

 

STANDARD CONNECTION

Connection of the Customer’s electrical installation according to such parameters:

  • load up to and including 160 kW;
  • distance of up to 300 meters in a straight line to the operating networks of the electrical transmission organization.Стандартное присоединение.

Obligations of Customer:

  • application for accession;
  • joining fee.

Responsibilities of power transmission organization:

  • training and issuance of TC;
  • carrying out of design and estimation documentation (then points of connection of electrical installations of the Customer);
  • construction, installation, commissioning.

Financing:
100% of the Customer’s funds in form of an adhesion fee (taking into account the withdrawal of Customer’s expenses for the execution of relevant project works).

 

 

NON-STANDARD CONNECTION

Connection of Customer’s electrical installation which corresponds to one of such parameters:

  • load exceeds 160 kW;
  • Distance over 300 meters, in a straight line, to the operating circuits of the electrical transmission organization;
  • voltage level at the coupling point differs from the voltage at the power supply point.

And the addition of electrical installations for the production of electrical energy, regardless of the installed capacity, is a non-standard connection.

Obligations of Customer:

  • application for accession;
  • development and negotiation of project estimates (for the construction of the linear part of accession);Нестандартное присоединение
  • construction and installation works from the point of attachment to the facility;
  • joining fee.

Responsibilities of power transmission organization:

  • preparation and issuance of design and TC specifications;
  • development and harmonization of project documents (except for linear part of connection);
  • execution of construction and installation works, commissioning of electrical installations up to the point of joining of Customer.

Financing:
100% of the Customer’s funds in form of an adhesion fee (taking into account the withdrawal of the Customer’s expenses for execution of the relevant project works).